Schedule Compliance Report

This report provides visibility into performance regarding meeting commitments to schedule. You can generate this from the Report Generator.

Required access roles:

  • Baseline: Reader
  • App-specific: Global User

  1. Click Home .
  2. In the navigation pane, click Program Mgmt > Reports.
  3. Click the Report Generator tab.
  4. Click the Refinements filter.
  5. Select the filters to view the results on the right side of the page.
    Field NameDescription
    Report TypeSelect Schedule Compliance Report.
    Report Sub TypeThe Schedule Compliance Report does not have sub types.
    Responsible OrganizationClick to select the responsible organization.
    ProgramClick to select the program related to the submittals.
    ContractClick to select the contract related to the submittals.
    Project Click to select the project related to the submittals.
    Date UnitSelect the date unit.
  6. Click Filter.

The Schedule Compliance Report is generated showing the number of late submittals with respect to the total number of submittals.

Note: Submittals will display only if the contract is connected to an active program.