With a Resource Table
You can use the resource table option.
- Click Sequence Combination
to create a combination of operations.
- Click Query Component
.
- Click Bind Object
.
- Double click the Bind a PLMComponent.1 operation
in the tree and enter
ExtObj
in the Relative Name field. Click OK to validate. - Click Knowledge Certify
.
- Expand the Bind a PLMComponent.1 and the QueryComponent.1 nodes.
- Double-click KWCertify.1 in the tree. The KWCertify.1
editor opens.
- Click Resource Table RuleSet.
- Click .... The resource table opens.
- Select a resource or click Add a new resource item.A new line appears in the table.
- Double-click the Resource cell.The Select a PLM Rule Set for item "Resource1" tab opens.
- Click Search and select the desired reference from the list. Click OK to validate.
- Click the Object field in the Feature to certify area and click the output link of the Bind a PLMComponent.1 operation in the tree. Click OK to validate.