| Name | Type a name for the impact analysis or
check the AutoName check box. |
| Description | Type a description for the impact
analysis. |
| Severity | From the list, select the level of severity for the analysis. Typical values are Low, Medium, and High. |
| Quality Impact | How the quality of the product
will be affected by the engineering change. |
| Lifecycle Cost Issues | Any issues about lifecycle
costs. |
| Prioritization Benefit | A number indicating
the priority of the perceived benefit. |
| Relative Cost | The relative cost to be incurred,
rated on a scale of 9 (highest) to 1. |
| Relative Penalty | The relative penalty, rated
on a scale of 9 (highest) to 1. |
| Relative Risk | The relative risk involved,
rated on a scale of 9 (highest) to 1. |
| Impact Analysis Effort | The number of days
to determine what the impact will be on products and schedules. |
| Estimate Schedule Impact | The estimated number
of days to be added to the schedule due to the engineering change. |
| Implementation Effort | The number of days to
resolve the engineering change (development + analysis). |
| Validation Effort | The number of days to validate
the engineering change. |