Task Status
|
A green arrow means that all route tasks are on time. A yellow
diamond means at least one route task, not including the last task
in the route task, is late. A red square
means that the last task is late. |
Name
|
The Name assigned to the task. |
Title
|
Title from the task. |
Approver
|
The person (you) assigned as the approver for this
task. |
Due Date
|
Shows the date that the task is due. For a Project
Task, shows the estimated end date. |
Approval Status
|
Box where you can enter the status
for the task. This table shows the available options for some types
of tasks:
Task Type |
Approval Status Options
|
Route with task action set
to Approve |
Select an Action Approve Reject Abstain
|
Route with task action set
to Comment |
Select an Action Complete
|
Route with task action set
to Notify only |
Blank when route is not
started Select an Action Accept |
Project tasks |
Select an Action Complete
|
|
Object
|
The object to be approved or rejected. Clicking
the name opens the object's page:
- For a route task, opens the properties page for the routed
object.
- For a project task, opens the properties page for the
project.
|
Comments
|
Box where you explain your choice for approval
status. If you select an approval status other than "No
Action," you must enter a Comment. If you enter a comment
and do not select an approval status for that task, the comment
is entered and the task remains open when you click
Done. Your Business Administrator can remove the