From the Civil
Engineering/Road/Railway
section of the action bar,
click Civil/Road/Railway Linear Stretch
.
The Road Linear Stretch dialog box is displayed.
It is highly recommended to avoid using overlapped stretches as input.
-
To concatenate earthworks and/or subgrade layers, select the results you want to
compute in the Generate list:
-
All: consolidates both earthworks and subgrade layers.
-
Only terrain-related results: consolidates only
earthworks.
-
Only subgrade layer: consolidates only subgrade
layers.
The linear stretch command can accept subgrades and earthworks. The inputs of linear
stretch may contain earthworks and/or subgrade layers. You can consolidate subgrade
layers in one linear stretch, and terrain-related results in another one.
-
Click Show Preferences
, and select the
Enable the creation of publications check box to publish the
subgrade layers.
-
To apply a default gap to two consecutive earthworks, set a value in the
Default Gap box of the Linear Stretch
window.
A message asks you if you want to reset the value of the existing gaps or apply the new
default gap only to new ones. When the Default Gap is equal to 0m
in the Linear Stretch dialog box, the User
Gap is automatically set to 0.5m.
When you select an input, the User Gap cell is set to the value
of the default gap.
-
To apply different values to different gaps, edit the gap value in User
Gap column.
-
To list inputs along the linear stretch alignment, click an item under the
Start Station column of the Linear Stretch
dialog box and select the Order along the alignment contextual
command.
By default, the inputs are listed according to its selection order.
-
Click Apply or OK when satisfied.
A transition is created to concatenate adjacent subgrades/earthworks. It is also
applied to subgrade layers. The different subgrade/earthwork stretches are now
considered as a unique stretch, which facilitates the terrain modification later on. The
intermediate gaps or, abrupt or overlapped sections are automatically filled or adjusted
as shown in the image below.
The common/excavation/filling stretches are updated.
-
To edit a linear stretch, double-click it.
|