In the tree, double-click the Grid Virtual Stacking to update.
The
Virtual Stacking dialog box is displayed, with the following stacking:
-
Double-click the empty C1 cells in rows (Sequence.16 and
Sequence.21) with 0 direction.
-
This valuates the direction of those
cells to 0 in the virtual stacking:

-
In the information table,
the cell has turned white, the number of plies for that cell is correct
:

-
Proceed as explained above for all cells in red in the information table.
-
Click Options.
- In the 3D display option dialog box, select Thickness law and click Close.
- Click OK to validate and exit the Virtual Stacking dialog box.
You can now inspect the model in the
work area.

-
Click Synchronize Stacking
and select the Grid Virtual Stacking.
- Click Launch Analysis.
The Synchronize Stacking And Virtual Stacking dialog box appears and is
populated.
The last column gives you the status of each ply.
-
Click Launch Synchronization to synchronize the plies that need to and exit the dialog box.
The initial plies were:

They have been updated to: