Synchronization manager dialog contains user preferences that are not active, in the
preferences panel:

- Check Detail Modification Status by Revision: Selecting this
option, a detailed modification status by revision of the Structure Plate displays.
- Allow Force Update to Re-trigger Rules the section has Weld Rule
and Opening Rule options.
- If Weld Rule option is selected, you can force a trigger weld
rule by selecting the Update with Rule action for the weld
line.
- If Opening Rule option is selected, you can force a trigger
opening rule by selecting the Update with Rule action for the
opening.
- If Check Detail Modification Status by Revision option is selected,
a detailed modification status of the Structure Plate objects in EBOM is displayed in braces
as described below:
- If the Material or Thickness of the plate (or panel) is different compared to the
previous revision of the plate (or panel), then the status is shown as
Modified (Spec)
- For all other modification, the status is shown as Modified
(Geo)

- Modification status of manufacturing features:
- If Weld Rule option is clicked in Preference, the status of the
Weld Line is displayed as Overridden if
the weld features are different from the weld rule.
- If Opening Rule option is clicked in the Preference, the status
of the opening is displayed as Overridden if the opening type is
different from the opening type returned from the rule.

- Force update to retrigger rules:
- If Weld Rule option is selected, Update with
Rule option is available additionally in the action column for the weld
line. If Update With Rule is selected, the weld rule is executed
and the weld features update according to the weld rule.
- If Opening Rule option is selected, Update With
Rule option is available additionally in the action column for the Opening
feature. If Update With Rule is selected, the opening rule is
executed and the opening feature is updated accordingly.

As shown, when the status of the feature is Up-To-Date,
execute the weld rule with Update With Rule option.

If the status of the feature is
Modified, execute the rule with Update With
Rule option, or you can only update the feature trigger with the
Update option.