Adding Choreography Activities

This describes how to use the Add Choreography Activity commands.

Click Play to watch the video:

  1. From the Bread Crumb bar, right-click GO TO activity and select Add Choreography Activity.

    Choreography dialog box appears.
  2. Select Create Color Event .
    Color Action dialog box appears.
  3. Click a part from the bike.
  4. From the Color Action dialog box, select a color.
  5. Enter a duration.
  6. Click OK.
    Creates a color action event.
  7. Select Create Text Event .
    Text Action dialog box appears.
  8. Enter duration, title, and detail information.
  9. Click OK.
    Creates a Text action event.
  10. Select Create View Point Event .
    View Point Action dialog box appears.
  11. Zoom in the screen to create a view point. In the View Point Action dialog box , Click insert . Enter duration in the viewpoint created.
    Creates a new viewpoint.
  12. Zoom out the screen to create another viewpoint. In the View Point Action dialog box, Click insert image. Enter duration in the viewpoint created. Click OK.
    Creates another viewpoint.
  13. Close the Choreography dialog box.
  14. Click Simulation State to position the manikins to original position.
  15. Click Simulate Task.
  16. Click Exit .