Specify Operations - Children Rows of Multiple Operations

You can specify Children rows for multiple operations.


Before you begin: If selecting a Parent Row of children rows together, this ignores the children selection and considers as a Parent Row case.
  1. Select Selected Operations in Operation Tree dialog, Operations of children rows.
  2. Select two children row of multioperations and click Set Operations in the context menu.


  3. Select three operations in the Operation Tree dialog and click OK.


    Remove Material Operation_Beams operation is remaining and Loading Operation_Beams is replaced with Loading Operation_Slabs operation. Point Fastening Operation_Slabs is added as the new child row.

  4. Select Operation in Operation Tree dialog = Operations of children rows.
  5. Select one child row of multioperations and click Set Operations in the context menu.
  6. Select Unloading Operation_Beams operation and Click OK.


    Loading Operation_Beams is replaced with Unloading Operation_Beams. And its parent is changed to the LEVEL2-BEAMS system according to the rule.

  7. Select Operation in Operation Tree dialog, Operations of children rows.
  8. Select two children rows of multioperations and click Set Operations in the context menu.
  9. Select Unloading Operation_Slabs operation and Click OK.


    Unloading Operation_Slabs is remaining for selected rows and its parent is changed to LEVEL_2_Slabs according to the rule.