Display the System
-
Create a data model with resource and system structures.
-
Switch to the Equipment Allocation app.
-
Define the resource-system scope for the root system and the root resource.
-
Assign General System 2.1 to Robot1, using either dragging or the
Assignement Manager.
-
Launch the Resource Utilization Gantt chart on the Manufacturing
Cell resource.
-
Expand the Robot1 row.
The Resource Utilization Gantt chart displays the system
and its children under the assigned resource Robot1. 
Notes:
- Operations that are not assigned to any resource (by implicit or explicit
assignment) display in the Unassigned Operations section of
the Resource Utilization Gantt chart.
- The systems assigned to resources display along with their children.
Drag a System on a Resource
-
Create a data model with resource and system structures.
-
Switch to the Equipment Allocation app.
-
Launch the Resource Utilization Gantt chart on the Manufacturing
Cell resource.
-
Expand the Robot1 row.
The Resource Utilization Gantt chart displays the system
and its children under the assigned resource Robot1. 
-
Select General System 2.1 under Robot1 and drag it to Worker2, without pressing
Ctrl.
The existing system link is removed from Robot1, and a new link is created
between the system and the target resource. 
-
Select General System 2.1 under Worker2, and drag it to Worker1, while pressing
Ctrl.
The existing system link is removed from Robot1, a new link is created between
the system and the target resource. 
-
Select General Operation 2.1 A under General System 2.1, and drag it to Robot1.
The operation is assigned to Robot1. 
|