- In the Programming section of the action bar, click Split Task.
. - In the Behavior side tab, select a task to split.
The Split Task panel appears. - Select the activity in the Activities list where the split is to occur.
- Enter a name for the new task and click Split Task.
The new task is created, and contains the selected activity and all activities that follow it in the sequence. The original task now only contains the activities prior to the one that was selected.
Example:
Before the split |
After the split |

|

|
|