Title
|
Enter a phrase or title for the change action.
|
Description
|
Describe the required change.
|
Severity
|
Select Low, Medium, or High.
|
Governing CO
|
The change order to which the change action is to
be associated. The change order governs the change.
|
Governing CR |
The change request to which the change action is to be
associated. The change request governs the change.
This field appears only when you create a change action for a
change request.
|
Due Date
|
Click
to select the date when the review must be completed.
|
Estimated Start Date
|
Click
to select the date when the review must start.
|
Change Order
|
Click
to select a change order type or subtype.
|
Assignees
|
Click to select the person assigned to complete
the change action. The assignee must be a Contributor or a Leader
from the same organization and project as the change
action. |
Approvers
|
Click to select the person who is responsible for
impact analysis and technical approval of the work on the change
action. The approver must be a Reader, Contributor, or a Leader
from the same organization and project as the change action. At
least one approver must be a Leader from the same organization
and project as the change action. |
Informed Users
|
Click
to select who will be notified that the change action is
released.
|