Click Done to generate the Metrics Report.
The following is an example of a metrics report. If you choose a comma as the delimiter, you can 
import that data into a spreadsheet program.
Type,Name,Revision,Description,Originator,Category of Change,Responsible Design
                Engineer,ECR Evaluator,Current State,Draft,Submit,Evaluate,Review,Plan
              ECO,Complete,ProductLine,Change Board 
ECR,ECR-4010,-,, DesignEngineer,Drafting Error, DesignEngineer, 
DesignEngineer,Complete,Thu May 17, 2001 11:47:29 AM EDT,Thu May 17, 2001 11:48:08 AM 
EDT,Thu May 17, 2001 11:48:08 AM EDT,Thu May 17, 2001 11:48:08 AM EDT,Thu May 17, 2001 
11:48:08 AM EDT,Thu May 17, 2001 11:48:08 AM EDT,Dirt Bike,Sample Change Board 1
ECR,ECR-4020,-,,DesignEngineer,Drafting Error, DesignEngineer, DesignEngineer,Plan ECO,Thu 
May 17, 2001 11:47:30 AM EDT,Thu May 17, 2001 11:48:08 AM EDT,Thu May 17, 2001 11:48:08 AM 
EDT,Thu May 17, 2001 11:48:08 AM EDT,Thu May 17, 2001 11:48:08 AM EDT,,Dirt Bike,Sample 
Change Board 1
ECR,ECR-4040,-,,DesignEngineer,Drafting Error, DesignEngineer, DesignEngineer,Create,Thu 
May 17, 2001 11:47:33 AM EDT,,,,,,Race Bike,Sample Change Board 2
ECR,ECR-4090,-,,DesignEngineer,Drafting Error, DesignEngineer, DesignEngineer,Create,Thu 
May 17, 2001 11:47:39 AM EDT,,,,,,Super Bike,Sample Change Board 2
ECR,006000,-,, DesignEngineer,Drafting Error, DesignEngineer, DesignEngineer,Plan ECO,Thu 
May 17, 2001 11:48:44 AM EDT,Thu May 17, 2001 11:48:48 AM EDT,Thu May 17, 2001 11:48:48 AM 
EDT,Thu May 17, 2001 11:48:48 AM EDT,Thu May 17, 2001 11:48:48 AM EDT,,,,,,,