Precedence Constraints Context Toolbars

The Precedence Constraints context toolbars provide commands for you to create constraints between activities (assembly sequences, tracks, and animations) in the Assembly Sequence Gantt chart. The available commands depend on how you drag activities in the Gantt chart. You can insert activities before, after or in parallel with the target activity.

This page discusses:

Context Toolbar for Inserting an Activity Before the Target Activity

For more information, see Constraints between Activities



Insert before activity with precedence constraint

Inserts activity before target activity with precedence constraint to create a precedence constraint between the two activities. Existing constraints to the target activity are replugged on the moved activity.



Add before activity with precedence constraint

Adds activity before target activity with precedence constraint to create a precedence constraint between the two activities. Activity is moved to the target activity with the constraint. Other constraints to the target activity are kept.



Create precedence constraint

Creates precedence constraint between the two activities. A new constraint is added between the activities. Other existing constraints along the activities are kept.



Insert before activity with synchro End-Start constraint

Inserts activity before target activity with synchro end-start constraint to create an end-start synchronization link between the two activities. You can set a delay between the end of one activity and the start of the other.



Add before activity with synchro End-Start constraint

Adds activity before target activity with synchro end-start constraint to create an end-start synchronization link between the two activities. You can set a delay between the end of one activity and the start of the other.



Create synchro End-Start constraint

Creates synchronization end-start between the two activities.



Cancel drag and drop

Context Toolbar for Inserting an Activity After the Target Activity

For more information, see Constraints between Activities.



Insert after activity with precedence constraint

Inserts activity after target activity with precedence constraint to create a precedence constraint between the two activities. Existing constraints to the target activity are replugged on the moved activity.



Add after activity with precedence constraint

Adds activity after target activity with precedence constraint to create a precedence constraint between the two activities. Activity is moved to the target activity with the constraint. Other constraints from the target activity are kept.



Create precedence constraint

Creates precedence constraint between the two activities. A new constraint is added between the activities. Other existing constraints along the activities are kept.



Insert after activity with synchro End-Start constraint

Inserts activity after target activity with synchro end-start constraint to create an end-start synchronization link between the two activities. You can set a delay between the end of one activity and the start of the other.



Add after activity with synchro End-Start constraint

Adds activity after target activity with synchro end-start constraint to create an end-start synchronization link between the two activities. You can set a delay between the end of one activity and the start of the other.



Create synchro End-Start constraint

Creates synchronization end-start constraint between the two activities.



Cancel drag and drop

Context Toolbar for Inserting an Activity in Parallel with the Target Activity

For more information, see Constraints between Activities.



Add activity in parallel with synchro Start-Start constraint

Adds activity in parallel with synchro start-start constraint to create a start-start synchronization link between the two activities. The activities start at the same time.



Create synchro Start-Start constraint

Creates synchronization start-start constraint between the two activities.



Add activity in parallel with synchro End-End constraint

Adds activity in parallel with the synchro end-end constraint to create an end-end synchronization link between the two activities. The activities start at the same time.



Create synchro End-End constraint

Creates synchronization end-end constraint between the two activities.



Cancel drag and drop