Click Play to watch the video:
-
From the Simulation section of the action bar,
click New Assembly Sequence
.
In the Gantt chart, right-click Assembly Sequence and
select Add Existing Activity.
-
Press F3 to display the tree.
-
In the tree, select the third system.
The third system is added to the assembly sequence.
-
In the same way, add the Text Action in the assembly sequence.
-
In the Gantt chart, drag the Text Action and drop it onto an operation.
A constraint is defined between the Text Action and the operation.
-
Click Product Build-Up Options
at the
right edge of the work area.
-
From the Display section of the Product Build-Up
Options panel, select Show Build-up Colors OFF.
-
In the Excitations panel
, select the Assembly Sequence thumbnail.
-
Click Play in the Compass to simulate the sequence.
-
In the work area,
select Analyze interferences
to
display the clash information table.
Contacts are detected between the Air Filter Cover and the two Air Filter
Bolts.
The two bolts are highlighted in red.