Create Tracks Under Operations from the Gantt Chart

In this first step, you will display the Gantt chart and create tracks under operations.


Before you begin: You must have suitable Manufacturing Planning data (systems/operations) in a PPR Context loaded in the Assembly Evaluation app.

Click Play to watch the video:

  1. Click Product Build-Up options at the right edge of the work area.
  2. From the Display section of the Product Build-Up Options panel, select Show Build-up Colors ON.
  3. From the Simulation section of the action bar, click Show Gantt Chart .
  4. In the Gantt chart, select operations.
    The related parts are displayed according to the defined build-up colors.
  5. In the Gantt chart, right-click an operation and select Create Track.
  6. Move the part.
  7. In the Track Authoring context toolbar, click Record and OK .
    The track is created and added to the Gantt chart under the operation.
  8. In the same way, create tracks for the Air Filter Cover and the two Air Filter Bolts.
  9. In the Gantt chart, select the third system.
  10. Click Play in the Compass to simulate the tracks.