From the Pit Optimization section of the action bar,
click New Processing
.
Alternatively, in the tree, double-click Processing in the Pit Opt case
underneath the Scenario category, and select New
Processing.
-
Underneath the Pit Opt case scenario instance, double-click the processing
node, and select New processing from the context menu.
-
In the New processing dialog box, enter a descriptive
Name
-
From the Rock Type Attribute list, select the required ore, and
click Add Path. You can add as many paths as required.
Selecting the rock type attribute determines which codes or technical regions
can be selected in each path of the Rock Type that is considered.
-
Select the code from the Rock Type list. Only codes related to
the Rock Type Attribute you selected, are available.
-
Enter a value for the Processing Cost.
The associated values required for Commodity,
Cost, Recovery percentage, Min
Grade and Max Grade are provided in the table for
each path.
-
Click Ok.
|