Name
| The name of the design project. Design projects can be expanded by clicking "+" to see their subprojects. When expanded, any level of subprojects will be displayed in one level. |
| The status flags indicate whether the
design project's tasks are behind schedule. The project's status flag reflects
the status of the task that is most behind. The exact number of days
for a task status to be yellow or red is configurable and may be different
for your system.
- No flag: the task is not late.
- Green: the task is complete.
- Yellow: the task is not complete and the days remaining are less
than or equal to the threshold.
- Red: the task is not complete and the system date is greater than
the estimated End Date or Base Line End Date.
|
Current Phase | The current phase for the design project or subproject. |
Type | The type is Design Project. |
Status | The design project's current
lifecycle state. For a description of the states, see Project Space Lifecycle. |
Owner
| The current owner of the design project, which
is the person who has primary responsibility for it. |
Collaborative Space | The collaborative space for the design project. |
Estimated Finish Date | The date the design project
should be completed. |
Actual Finish Date
| The date the design project was promoted
to Complete. The system automatically promotes a project to Review when all its tasks are Complete. |
Originated | The date the design project was created. |
Program
| The programs the design project is assigned
to. |
Description | The description of the design project. |