Enter details for the task:
Type. Select this from the list. You can choose Task,
Phase, Gate, or Milestone.
Note:
You cannot select a task type specific to Market Registration, such as an Interactive Review, Review Question, or Regulatory Milestone.
Create those specific task types in Market Registration.
Number. The number of tasks to create.
Name. The name of the task, which cannot exceed 127
alphanumeric characters. Click Autoname to have the
system assign the task name.
Description. A brief description of the task. Must be
alphanumeric characters.
Insert. Choose to insert the task
Above or .
Duration. An estimate of the task length. The Duration must be less
than 10,000 days. Sub Level Enter a number (can
include a decimal value) and select units (days or hours) from the list. If
a Duration Keyword is specified, the value for the
Duration is populated with the default duration value defined with the
keyword. Milestones/Gates created with the Project Review policy always has
a zero duration. Task (Task/Phase/Gate/Milestone and their subtypes) created
with the Project Task policy always has a nonzero duration.
Start Date. The start date of the task. Available only for types
"Task" and "Phase." Not available for a template.
End Date. The end date of the task. Available only for types "Task"
and "Phase." Not available for a template.
Constraint Type. The type of constraint for this task,
which specifies when the task is expected to be completed within the
project.
For nonsummary tasks, values can be "As Late as Possible," "As Soon as
Possible," "Start No Earlier Than," "Finish No Earlier Than," "Start No
Later Than," "Finish No Later Than," "Must Finish On," or "Must Start On."
For summary tasks, values depend on whether the project schedule is from the
start date or finish date.
Constraint Date. Constraint types other than "As Soon
as Possible" or "As Late as Possible" have a constraint date.
Calendar. You can select the calendar for scheduling
the task. If a task does not have a calendar connected to it and has only
one assignee, the assignee's location calendar is used for project
scheduling. If a task does not have a calendar connected to it and has
multiple assignees, the default project calendar is used for scheduling. The
project calendar overrides a task calendar if scheduling conflicts occur
between calendars. For example, if a project has a start time at 9.00 Hr and
its subtask has another calendar connected which has a "Work Start Time" at
8.00 Hr, then the task starts at 9.00 Hr.
Policy. Select the policy for the selected task type.
Gate and Milestone task types follow the "Project Review" policy. Task and
Phase task types follow the "Project Task" policy.
Task Requirement. Indicates whether this is an
optional or mandatory task. The system's default behavior requires all
tasks, even optional ones, to complete before the project itself can be
complete.
Owner. Click the check box to search for the person
who is the task owner. If you do not choose this option, you become the
owner and be included in the assignees list.
Assignee. Click the box to search and find persons you
want to assign this task to. You do not have to assign the task now. After
creating the task, an assignee from outside the project can be added.
Needs Approval. Indicates whether the task requires
approval. If "Yes" the task goes to the "In Approval" state when the
"Percent Complete" for the task is 100%. If "No" the task goes to the
"Completed" state directly when the "Percent Complete" for that task is
100%. Available only if the Policy is "Project Task."
Note:
If you promote all leaf tasks to the "Completed" state, the summary task
moves to the "Completed" state if the "Needs Approval" attribute for the
summary task is "No."