BOM Markup Overview
Markups are required to implement changes for assemblies that are not in the Preliminary state. Two kinds of markups can be created in the Bill of Materials page Plant Preferences View: EBOM markups, which always require a CO to implement, or Plant BOM markups, which can be implemented using an MECO.
If an MECO is used to implement only plant-specific changes, then the assembly item is added to the MECO as an affected item. In this case the value for the Requested Change attribute would be “For Update.”
In this case, no new revision is created and changes are applied to the same released revision.
If a CO is used to implement EBOM changes, then the assembly item is added to the CO as an affected item. In this case the value for the Requested Change attribute would be “For Revise.”
In this case, a new revision is created and both the markups are applied to the new revision.
Note: When there are both EBOM and plant changes in the Plant Preferences view, then both MECO and CO selection are required.