To have an overview of how the operations are balanced on the resources, from
the Authoring section of the action bar, click Resource Balancing
, then click the workers' Manufacturing Cell.
The work load is not evenly balanced among the workers.
-
Close the Resource Balancing panel.
-
Control-click Worker 1 and 2, then click
Resource Balancing
again.
-
In the Resource Balancing panel of Worker
1: select operations at the top of the column and drag them on
Worker 2
Resource Balancing panel, at the bottom of the
column.
Note:
In the columns, the order of operations starts from the bottom.
-
To display more detail about the operations and resource balancing, from the
Authoring section of the action bar, click Resource Utilization Gantt
and click the workers' Manufacturing Cell.
The operations are now balanced on the resources.