Click a system or an organizational resource scoping a system, and from
the Authoring section of the action bar,
click Synchronizing Data with Planning
.
The Programming Context dialog box
appears.
- Select Assembly and click OK.
The Synchronizing data with Planning panel appears. The panel includes:
- Planning System: The selected system
that is scoped by the selected resource.
- Operation Level: The level of depth
of listed operations. If the level is 1, then all operations
under a system are displayed. If the level is 2, then all
operations under a system + their operation children are
displayed. If the level is 3, then all operations under a
system + their operation children + their operation grand
children are displayed, and so on.
- Select the Location: Sets the
organizational resource for the location of the
Manufacturing product creation for the selected rows. The
command is grayed when no row is selected.
- Synchronize data with planning for the selected
rows: Creates or updates the corresponding
Manufacturing product for the selected rows at a specified
location. The command is grayed when no row is
selected.
- Operation: The name of an operation
occurrence.
- Manufacturing Product: The name of the
generated Manufacturing product, if any.
- Assigned Resource: The assigned
executing resource, if any.
- Location: The name of the
organizational resource owning the manufactured product,
parents of the assigned resource, or the resource scoping
the selected system, if any.
- Status: The status of the content of
the Manufacturing product. Yellow signifies when no
Manufacturing products have been created. Red signifies when
the content of the associated Manufacturing product is
different from the corresponding planning operation. Green
signifies when the content of the associated Manufacturing
product does not need to be updated.
- Specify the parameters and double-click a row to bring up the panel shown in previous section. Create/ update the manufacturing product for the selected operation and click OK.
This creates the planned Manufacturing Product as specified in the Synchronizing data with Planning panel for the planning system. The Status in the Synchronizing data with Planning panel will be green to indicate an updated status.
|