- From the Authoring section of the action bar, click Create End-Start Link
. - Select two operations in the order of the following constraint:
The first operation must end at the same time that the second one starts.
- Optional: In the Set Delay dialog box, enter a fixed delay between the end of the first operation and the start of the second one, then click OK.
Note:
To edit the delay, double-click the arrow in the Process
Gantt or right-click the arrow and click
Constraint Properties
.
The end-start link is created:
- In the Process Gantt

- In the System Editor