Right-click an operation, and select Properties.
-
From the Time Mode list, select Estimated
Time.
-
In the Estimated Time field, enter a value greater than the time
you expect the operation to take.
Note:
If the Estimated Time is smaller than the actual duration computed for
the operation, then the simulation stops at the Estimated Time value, even if the
operation has not been completed.
-
Load your data in an app that supports level 3 simulation (Behavior and
Associated Detailing simulation mode), for example:
- Assembly Definition
- Assembly Evaluation
- Assembly Experience
- Assembly Path Optimization
- Ergonomics at Work
- Ergonomics Evaluation
- Robot Simulation
-
Click Play to launch the simulation.
-
Update the Simulation Options:
-
Check the Update Cycle Time option.
-
Under Resource Simulation Level of Detail, select
Simulation Specifiation Behavior and Associated
Detailing.
-
Check the Graphics Update options.
-
Click Play again to launch the simulation one more time.
-
Load your data back into Process Planning.
-
Right-click the operation, and select Properties.
The Time Mode is now defined as Simulated
Time.
-
From the Authoring section of the acion bar, click
Process Gantt
and verify that the Simulated Time is updated.
|