Using
Collaboration for Microsoft
you can:
- Create projects in
Project Management
from Microsoft Project.
- View existing
3DEXPERIENCE
projects in Microsoft Project.
- Open and modify an existing Project Management project in Microsoft Project and save the
changes back in 3DEXPERIENCE.
- Save from Compare and Show my changes view is allowed only when at
least one difference between Microsoft project and 3DEXPERIENCE data has been
synchronized.
- In Microsoft Project Integration when you change an attribute of any
one of the tasks, the attributes of other tasks may get changed in
3DEXPERIENCE. You can view the changes in the 3DEXPERIENCECompare View and
reload it to get the correct attributes of the tasks.
Note:
The actual dates of Summary task in Microsoft Project Integration and
3DEXPERIENCE Project Management for a specific scenario are not in sync. In
such cases, actual dates of summary task and child tasks are different in
Microsoft Project Integration than that of Project Management.