Predicted Task Effort

This chart displays predicted efforts for the next 4 upcoming weeks for active tasks.

Business Objects Task (data model class "task")
Values (or X-Axis and Y-Axis)
  • X-Axis: Task effort (task_task_total_effort).
  • Y-Axis: Week of the year.
Sorting The results are sorted by date, from oldest to newest result.
Limits Only the 4 incoming weeks.
Colors The chart is blue.
Available Views Bar chart.
Interactions On this chart, you can:
  • Click to switch to fullscreen display.
Technical Details
  • Data model
    • Class: document
      • Property: type
    • Class: project
    • Property: project_percent_complete
  • Mashup feed (project_history)
    • Aggregations added on facet type
      • effort_after_one_week: SUM(#int(project_percent_complete * project_estimated_duration / 100)> 0 ? (#float(#int(#sum(task_task_total_effort) / 100)/ #int(project_percent_complete * project_estimated_duration / 100)) * (remaining_days<6 ? (project_estimated_duration * (100 - project_percent_complete)) / 100: 5)) : 0)
      • effort_after_two_week: SUM(#int(project_percent_complete * project_estimated_duration / 100)> 0 ? (#float(#int(#sum(task_task_total_effort) / 100)/ #int(project_percent_complete * project_estimated_duration / 100)) * (remaining_days<11 ? (project_estimated_duration * (100 - project_percent_complete)) / 100: 10)) : 0)
      • effort_after_three_week: SUM(#int(project_percent_complete * project_estimated_duration / 100)> 0 ? (#float(#int(#sum(task_task_total_effort) / 100)/ #int(project_percent_complete * project_estimated_duration / 100)) * (remaining_days<16 ? (project_estimated_duration * (100 - project_percent_complete)) / 100: 15)) : 0)
      • effort_after_four_week: SUM(#int(project_percent_complete * project_estimated_duration / 100)> 0 ? (#float(#int(#sum(task_task_total_effort) / 100)/ #int(project_percent_complete * project_estimated_duration / 100)) * (remaining_days<21 ? (project_estimated_duration * (100 - project_percent_complete)) / 100: 20)) : 0)