Business Objects |
Tasks (data model class "task ") |
Values (or X-Axis and Y-Axis) |
- X-Axis: task completion percentage (project_percent_complete).
- Y-Axis: Week of the year.
|
Sorting |
The results are sorted by date, from oldest to newest result. |
Limits |
Only the 4 incoming weeks are displayed. |
Colors |
The chart is blue. |
Available Views |
Bar chart. |
Interactions |
On this chart, you can:
- Click to
switch to fullscreen display.
|
Technical Details |
-
Data model
- Class: project
- Property:
project_percent_complete
- Mashup feed (project_history)
- Aggregations added on facet typeprogression_after_one_week:
SUM(((project_estimated_duration * (100 - project_percent_complete)) /
100)>5 ? ((((project_percent_complete * project_estimated_duration / 100)+5)
* (100-project_percent_complete)) / ((project_estimated_duration * (100 -
project_percent_complete)) / 100)) : 100)progression_after_two_week:
SUM(((project_estimated_duration * (100 - project_percent_complete)) /
100)>10 ? ((((project_percent_complete * project_estimated_duration /
100)+10) * (100-project_percent_complete)) / ((project_estimated_duration *
(100 - project_percent_complete)) / 100)) :
100)progression_after_three_week: SUM(((project_estimated_duration * (100 -
project_percent_complete)) / 100)>15 ? ((((project_percent_complete *
project_estimated_duration / 100)+15) * (100-project_percent_complete)) /
((project_estimated_duration * (100 - project_percent_complete)) / 100)) :
100)progression_after_four_week: SUM(((project_estimated_duration * (100 -
project_percent_complete)) / 100)>20 ? ((((project_percent_complete *
project_estimated_duration / 100)+20) * (100-project_percent_complete)) /
((project_estimated_duration * (100 - project_percent_complete)) / 100)) :
100)
|