Business Objects |
Project (data model class "task ") |
Values (or X-Axis and Y-Axis) |
- X-Axis: timeline (week unit), based on
history_weekofyear
facet
- Value and Y-Axis of timeline: aggregation value corresponding respectively to
SUM of
- Open tasks:
snapshot documents
(document_history_type field) without
complete category on facet current
- Late tasks:
snapshot documents
(document_history_type field) without
complete category on facet current and
with project_estimated_finish_date before
now
- Critical tasks:
snapshot documents
(document_history_type field) without
complete category on facet current and
with true category on facet
task_mgmt/critical_task
- Late tasks:
snapshot documents
(document_history_type field) without
complete category on facet current, with
true category on facet task_mgmt/critical_task
and with project_estimated_finish_date before
now
|
Sorting |
The results are sorted by time, the most recent on the right of the
chart. |
Limits |
Only the last 12 weeks are displayed. |
Colors |
The color of this chart is customizable and predefined to Red, Orange, Blue,
and Green for count of [0; 0.5[, [0.5; 1[, [1; 1.5[, [1.5; 100000[. |
Available Views |
Indicator values with history. |
Interactions |
On this chart, you can click the filter icon to refine dashboard on (respectively):
- Open tasks
- Late tasks
- Critical tasks
- Critical late tasks
|
Technical Details |
-
Consolidation
- These indicators rely on snapshots computed by
project_
getProjectHistoryFromEnovia aggregation
processor
- Data model
- Class: task (or inherited)
- Property:
document_history_datetime
- Property:
document_history_type
- Property:
project_estimated_finish_date
- Mashup feed:
project_history
|