Relations Update in 3D Shape Context
You can choose, when creating the relation, if it will be synchronous
(i.e. the evaluation will be launched as soon as one of its parameters is
modified) or asynchronous (i.e. the evaluation will be launched when the Part
is updated). Each relation can therefore be synchronous or asynchronous.
- Enable the creation of synchronous relations
-
Enables you to create synchronous relations, that is relations
that will be immediately updated if one of their parameters/inputs is modified.
Only relations based on parameters can be synchronous.
- Associate the evaluation of relations with the global update
-
Enables you to associate the evaluation of asynchronous
relations with the global update. Relations can be asynchronous for two
reasons:
- You want the relations to be asynchronous.
- The relation contains measures.
- Relations based on parameters: can be synchronous or
asynchronous.
- Relations based on geometry: can only be asynchronous.
- Relations based on parameters and on geometry: For the part
of the relations containing parameters, you decide if you want the update to be
synchronous or not. For the other part of the relations, the update occurs when
the global update is launched.
- Do not ask for confirmation or automatic update when creating a
synchronous relation
- Enables you not do display the
Automatic Update confirmation dialog box when
creating formulas and when
Creation of synchronous relations and
Creation of relations evaluated during the global
update are enabled.
Note:
This option is dimmed if
Creation of synchronous relations and
Creation of relations evaluated during the global
update are not enabled.