Plan
Project Leads, the project owner, and the Financial Reviewer define
cost and benefit categories and enter planned amounts for the categories.
Once the planned amounts are entered and stable, any of these people
can promote the budget to Plan Frozen.
Plan Frozen
Project Leads and the project owner can only enter estimated and actual
amounts for cost and benefit categories. They can only enter estimates
and actuals for a previous period if no amount has been entered for the
period. Once an actual is entered for a previous month, neither the estimate
nor the actual can be edited.
The Financial Reviewer can continue to update planned amounts. No
one can add new categories or delete categories when in Plan Frozen.