Displaying B.I. Essentials Colors in the Gantt Chart

You can select a B.I. from the B.I. Essentials list, to display colors in the Gantt chart to reveal information about operation status.

See Also
About the Resource Utilization Gantt
  1. Open your session data and start the required Manufacturing Planning application.

    In this example, Operation1 is assigned to Worker1. Operation2 is not assigned to a resource.



  2. Select the Manufacturing Cell organizational resource in the tree.
  3. From the Authoring section of the action bar, click Resource Utilization Gantt .
    The Gantt chart appears, showing the resource-operation view. The bars representing the operations are colored gray, which is the default color.
  4. From the Tools section of the action bar, click B.I. Essentials .
    The B.I. Essentials list appears.
  5. From the list, select Operation to Working Resource Assignment Status.
    The bars representing the operations are colored according to the B.I. colors. Operation1 is colored green and Operation2 is colored red.
  6. Assign Operation2 to Worker2 by dragging the operation on the resource in the tree.
    Both operations are now colored green in the Gantt chart.
    Note: When the B.I. Essentials list is closed, the bars representing the operations are colored gray again.