Open your session data and start the required Manufacturing Planning
application.
In this example, Operation1 is assigned to Worker1. Operation2 is not assigned
to a resource.
- Select the Manufacturing Cell organizational resource in the tree.
-
From the Authoring section of the action bar, click Resource Utilization Gantt
.
The Gantt chart appears, showing the resource-operation view. The bars
representing the operations are colored gray, which is the default
color.
-
From the
Tools section of the action bar, click
B.I. Essentials
.
The
B.I.
Essentials
list appears.
-
From the list, select Operation to Working Resource Assignment
Status.
The bars representing the operations are colored according to the B.I.
colors. Operation1 is colored green and Operation2 is colored red.
-
Assign Operation2 to Worker2 by dragging the operation on the resource in the
tree.
Both operations are now colored green in the Gantt chart. Note:
When the
B.I. Essentials list is closed, the bars representing the operations are
colored gray again.
|