Maturity of Deliverables Per Estimated and Actual Finish Date

This chart shows the number of deliverables by their estimated and actual finish dates for each week, broken down by the deliverables' maturity states.

It helps making sure that the overall progress of deliverables is on track. For example, if, for a given week in the past, there are more deliverables by estimated finish date than deliverables by actual finish date, it means that not as many deliverables as expected were delivered.

Business Objects
  • From Project Management: Tasks.
  • From Project Planning: Tasks.
Values (or x-axis and y-axis)
  • X-axis: Weeks.
  • Y-axis: Number of deliverables.
Sorting Chronologically, oldest to newest from left to right.
Limits No limits.
Available Views Stacked bar chart.
Interactions On this chart, you can:
  • Paginate through all chart entries by using the pagination.
  • Hide series.
  • Show underlying data by clicking Menu > See underlying data.
  • Increase the chart size by clicking > Maximize.