Planned and Realized Effort per Project

For each day, this chart shows the total planned and realized effort of tasks that are not in the complete state, grouped by project.

Business Objects From Project Management:
  • Person
  • % Allocated on task
  • Effort
Values (or x-axis and y-axis)
  • X-axis: Days.
  • Y-axis: Total planned and realized effort of tasks that are not in the complete state per project. In hours.

    For example, for a given day, assume a project with 2 tasks (Task A and Task B):

    For Task A:

    Plan effort for Assignee #1: 4 hours.

    Plan effort for Assignee #2: 2 hours.

    Total plan effort for Task A = 4 + 2 = 6 hours

    For Task B:

    Plan effort for Assignee #1: 2 hours.

    Plan effort for Assignee #2: 5 hours.

    Total plan effort for Task B = 2 + 5 = 7 hours

    Total plan effort for the project = total plan effort for Task A + Total plan effort for Task B = 6 + 7 = 13.

    For this project on this given day, the chart displays 13.

Sorting Chronologically, oldest to newest from left to right.
Limits No limits.
Colors One color per project.
Available Views Bar chart.
Interactions On this chart, you can:
  • Paginate through all chart entries by using the pagination.
  • Increase the chart size by clicking > Maximize.
Technical Details