Copying Activities

You can copy activities that you have already created and reuse them in other portions of the process.

Copying activities creates an independent version of the activity. Once created, there is no link between the two activities. You can alter one without making changes to the other, as desired.

  1. Open a simulation process.
  2. Right-click the activity that you want to copy, and select Copy.
  3. Position the pointer where you want to place the copied item, right-click and select Paste.

    You can also select the item and use the typical keyboard shortcuts, such as the Ctrl-C and Ctrl-V functions.

    Automation Process Composer copies the activity to the process diagram. Any changes made to either item are not reflected in the other item.
  4. Optional: Paste the item again on the process diagram.