Views Update Status

The Views Update Status B.I. reveals information about the views associated with the operations.

Color Code

When the Views Update Status B.I. is clicked the Work Instructions app, the following colors appear in the Operations Sequencer panel:

Color Signification Description


Views update status is OK. The operations mark with blue if all views are up to date.
Note:
  • Operations of current Active-System mark with blue if the Views are up to date for both Process-Planning changes and Design-Position changes.
  • Operations of Non-Active-System mark with yellow if the Views are up to date for Process-Planning changes only. The verification for Design-Position changes does not account.


Views need to update. Operations mark with yellow if some or all of them have invalid views.
Note:
  • Operations of current Active-System mark with yellow if the Views need update either Process-Planning changes or Design-Position changes.
  • Operations of Non-Active-System mark with yellow if the Views need update for Process-Planning changes only. The verification for Design-Position changes does not account.


No views are associated with the operation. In this case, the operation marks with gray.