Fulfilling the Resource Requests

Once the resource request has been promoted, you can fulfill a resource request.

Required access roles:

  • Baseline: Leader
  • App-specific: Contracts Manager


Before you begin: A project and a task must exist.
See Also
Creating a Project
Creating Tasks
  1. List the app categories for Program and Contract Management.
  2. In the navigation pane, click Resource Requests.
  3. Click the Resource Request link.
  4. From the page toolbar of the Resource Request Properties page, click Fill Request .
    The Fill Resource Request page opens listing the available resources within the organization that satisfy the requirements of the request.
  5. Select the applicable resources that will fulfill the request.
  6. Click Done.
  7. From the resource request lifecycle, promote the state of the request to Filled.

An email notification will be sent back to the requestor that the request has been filled.