Choose the notification times and dates. The default is the exact due date and
time for the task (0 hours and days from the due date/time).
If required, change the notification time and date for any checked groups.
Define the relative time before or after the task due date/time that the
notifications will be sent, use the Escalate on Due
Date lists.
- Use the first list to indicate if the time will be added (+) or
subtracted (-) from the due date/time.
- Use the Days list to choose the number of days to add or subtract from
the due date.
- Use the Hours list to choose the number of hours to add or subtract from
the due time.
For example, suppose that you want to notify task assignees 2 days before the
task due date; route owners, 6 hours before; and Project Leads, 1 day after.
You would fill in the page so it looks like this:
Task Assignee - 2 Days 0 Hours
Route Owner - 0 Days 6 Hours
Project Lead + 1 Days 0 Hours