Creating Preassigned Work Center Links with Operations

You can define preassigned work center links on a first-level operation instance under the workplan.

The source of the preassigned work center link is the operation in the workplan context, which links to the assets structure. Its target is a work center reference.

Important: This capability is only available for first-level operations under the workplan.

This task shows you how to:


Before you begin: Open data containing an asset structure with at least one work center and a workplan with at least one first-level operation.