Select the root General system in the tree.
-
From the Authoring section of the action bar,
click Workload Balancing
.
The operations are automatically sequenced in the Gantt chart.
In the
Workload Balancing panel, the three systems are displayed in
columns, which are divided into operations. The General System C
exceeds the cycle time.
-
In the Workload Balancing panel, select the rectangle at the
bottom of General System C.
A tooltip gives information about the operation and the operation is highlighted
in the tree.
-
Drag the selected rectangle to the bottom of General System B.
The operation is added at the end of General System
B.
-
Drag more loading operations of General System C above the
previously moved operations.
The operations are now balanced on the systems.
The Gantt chart is
updated.