In this step, you will sequence operations using the Process Gantt chart.
Click Play to watch the video:
From the Authoring section of the action bar,
click Process Gantt.
Select the root System in the tree.
The Process Gantt appears showing all systems and operations. The operations are not sequenced at this stage.
In the graphic part of the Gantt chart, drag an operation to a second operation in the
Gantt chart.
A product flow appears between the two operations. The two operations are
sequenced.
In the same way, sequence the other operations in the Gantt chart.
Make sure that the percentage in the Utilization column complies
with the Utilization criteria. If the percentage is too big, the cell is colored
red.
Tip:
If the Utilization percentage is excessive, you can move operations from
the overloaded system to one that is less loaded or decrease the duration of one or more
operations.