Open a Resource Configuration GanttContext MenuA set of contextual commands is available for activities in the Gantt chart. When you right-click any row of the Gantt chart, the following commands are available in the context menu:
Assign a Precedence LinkYou can use the Resource Configuration Gantt to assign a precedence link. Drag an activity to another activity to create a precedence link. Note that loop definitions are checked to prevent issues. To remove a precedence link, right-click the activity and select Delete Constraint. You can select several operations using the Ctrl key. |