From the Pit Optimization section of the action bar,
click Scheduling.
-
In the Scheduling dialog box, select Enable
Scheduling.
-
In the General section:
-
Select the Maximum Period for scheduling. It can be either
Unlimited or a specific value.
-
Enter the Discount Rate for the discount factor the value
over time. The value is a percentage.
-
Enter the Mining Capacity for each period.
-
Enter the Processing Capacity for each period.
-
In the Bench Definition section:
-
Enter the Bench Height.
-
Enter the Start Level. The start level is used for counting
and flagging benches. Benches are counted from the top down.
-
In the Bench Sequence Rule section:
-
Click Fixed Lead to enable a fixed lead. A fixed lead means
that the bench of a phase cannot be mined for more than the specified number of levels
from the bench of a later phase.
-
Enter a Fixed Lead value.
-
In the Bench Sequence on Flitch section you can define the bench
sequence on the flitch. The flitch is a horizontal layer of blocks within a phase. Blocks
on a flitch can be sequenced either following a parallel direction or following a radial
direction:
-
Select either Follow Phase Direction or Parallel
Direction.
Follow Phase Direction means that the direction follows the
phase direction. To enable this feature select Enforce Phase to Follow a
Direction in the Pit and Phases panel.
Parallel Direction means that the direction is defined by
the angle of the direction relative to the Y axis going clockwise. If
Parallel Direction is selected, enter the required
angle.
-
Click Ok to save and close the dialog box.
|