On the Schedule page, click
Enable Edit
.
For a project or task, the page toggles to Edit mode.
-
If the task you want to work with is not visible, use the page
expand or filter tools to display it.
-
Click a task or project in the project hierarchy, click
Actions
, and select an option:
Add Project > Project Above. Inserts a
project above the selected task/project in the structure, as a sibling.
Add Project > Sub Project. Adds a child
sub project to the selected task/project.
If you are not a Project Lead, you can only add projects as sub
tasks to your assigned tasks. You cannot add siblings for your assigned tasks.
-
Check the projects that you want to insert or add.
-
Click OK. The projects are added to the schedule as
tasks.
|