On the Projects page, click the name of a project. See
Projects Page. In the
navigation pane,
click
Financials >
Budget tab.
A project can have only one budget.
-
For an existing budget, you can view the following information:
Item. The name of the budget. Also listed
are any cost categories and cost items in the budget.
Ledger A/C No. The ledger account number
associated with the cost item.
[Interval]. All-time intervals display for
the budget, along with cost amounts.
Total. The total cost of the budget appears
on the top line. Each cost category (cost center) has its own total of all the
costs in that category. Each cost item shows the total of all individual cost
items.
Variance. This column appears only in the
Estimated and Actual views:
In the Actual View:
- Variance Amount = Actual cost minus Plan cost
- Variance % = (Actual / Plan) X 100
In the Estimated View:
- Variance Amount = Actual cost minus Estimate cost
- Variance % = (Actual / Estimate) X 100
-
Use the filter
to change the
Currency for the amounts, the
Interval for the budget display, and the
View (Plan View to view basic plan
information, Estimated View to enter estimates, and Actual View to view
amounts).
|