The remaining effort planned for a Task. The following are algorithms
for calculating the remaining effort for a Task:
- The initial calculation of Remain Effort for an assignee =
Plan Effort for an assignee.
- The subsequent calculation of Remain Effort for an assignee
= previous Remain Effort for an assignee - Assignee
Submitted/Approved Effort.
- Total Remain Effort = sum of all assignees' remaining
efforts.
Below is an example, with the basis: Duration of the
task = 5 days Estimated Start Date = Monday, August 2,
2004 Estimated End Date = Friday, August 6, 2004
Assignee #1 is assigned 50% effort for the task.
Assignee #2 is assigned 75% effort for the task
Assignee #3 is assigned 100% effort for the task.
Remain Effort for Assignee #1 = Plan Effort = 5 * (0.5) *
8 = 20 hours. Remain Effort for Assignee #2 = Plan Effort
= 5 * (0.75) * 8 = 30 hours. Remain Effort for Assignee
#3 = Plan Effort = 5 * (1) * 8 = 40 hours. Total Remain
Effort = Total Plan Effort = 20 + 30 + 40 = 90 hours. At
the end of the 1st week (week ending August 7, 2004):
Assignee #1 submits 4 hours of effort. Remain
Effort for Assignee #1 = 20 - 4 = 16 hours Total Remain
Effort = 16 hours. Assignee #2 submits 16 hours of
effort. Remain Effort for Assignee #2 = 30 - 16 =14 hours
Total Remain Effort = 16 + 14 = 30 hours. Assignee
#3 does not submit any efforts. Remain Effort for
Assignee #3 = 40 - 0 = 40 hours Total Remain Effort = 16
+ 14 + 40 = 70 hours. Total Approved Effort = sum of
approved efforts = 0. Project Manager approves all
submitted efforts. Total Approved Effort = 4 + 16 = 20
hours. At the end of the 2nd week (week ending August
14, 2004): Assignee #1 submits 12 hours of effort.
Remain Effort for Assignee #1 = 16 - 12 = 4 hours.
Total Remain Effort = 4 + 14 + 40 = 58 hours.
Assignee #2 submits 8 hours of effort. Remain
Effort for Assignee #2 = 14 - 8 = 6 hours. Total Remain
Effort = 4 + 6 + 40 = 50 hours. Assignee #3 submits 16
hours of effort for last week. If Assignee #3 has effort
to submit from last week, the assignee must enter last week's
effort first. Remain Effort for Assignee #3 = 40 - 16 =
24 hours. Total Remain Effort = 4 + 6 + 24 = 34 hours.
Assignee #3 submits 16 hours of effort for this week
Remain Effort for Assignee #3 = 24 - 16 = 8 hours.
Total Remain Effort = 4 + 6 + 8 = 18 hours. Total
Approved Effort = sum of approved efforts = 20 hours.
Project Manager approves all submitted efforts.
Total Approved Effort = (20 previous approved) + 12 + 8 +
16 + 16 = 72 hours.
|