Enter these details:
Type. The type of object, typically
Opportunity.
Title. Enter a name for the opportunity.
Policy. Select the
Project Risk policy.
Description. A brief description of the
opportunity.
Visibility
- Public. Anyone who can view the project
can view the opportunity.
- Restricted. The opportunity owner,
assignees, project owner, and project leads can view the opportunity.
Estimated Start Date. The date on which the
opportunity owner expects the assignee to begin to work on the opportunity.
Click
to select a date.
Estimated Finish Date. The date on which
the opportunity owner expects the assignee will complete work on the
opportunity. Click
to select a date.
Opportunity Type. Values are Cost, Quality,
Technical, Resource, Performance, Schedule, Benefits, Manufacturability, or
Other.
Impact. The significance of the opportunity
to the organization. The values are 1 -5, with 5 indicating opportunities with
the highest value.
Probability. The probability of
accomplishing the opportunity. The values are 1 -5, with 5 indicating
opportunities most likely to be realized.
OPN.
Opportunity Priority Number. The system calculates
this value by multiplying the Probability value by the Impact value. You cannot
edit this field.
Effective Date. The date the opportunity
takes effect. By default, the current date is entered but you can choose a
different date. Click
to select a date.
Status. A brief status of the opportunity,
especially relative to the probability and impact values.