Choose values for the preferences:
Enable Approval. A value of TRUE enables the approval process for an
experiment project before it can be synced with its root project.
Schedule Based
On. Select whether the project is scheduled based on
Estimated start/end dates or
Actual start/end dates. If set to
Actual, when actual dates are entered for a task,
the project schedule is automatically recalculated.
When set to Actual, the following behavior occurs:
- As tasks start or complete, the actual start and finish dates also
reflect as the estimated dates. The actual dates are copied to the
estimated fields reflecting actual dates.
- The schedule recalculates, taking into account the actual dates that are
now reflected as estimated dates for those tasks that are started and
completed.
- When a task is completed, the estimated duration of the task is
overwritten reflecting the actual duration of the task taking into
account the actual start and finish dates. The duration unit is
maintained when the duration is updated to reflect the actual
duration.
- Tasks that are started or completed after normal working hours (for example, before 8 AM
or after 5 PM) are not counted toward the duration and those dates are
rounded to the next available working hours.
- The time for tasks started or completed between normal working hours
(for example, between 8 AM to 5 PM) will be set as the Work Start Time
(for example, 8 AM) for the Actual Start Date and the Work Finish Time
(for example, 5 PM) for the Actual End Date.
- Dependencies and constraints are ignored while calculating dates when a
task has an Actual Start Date.
Schedule. Choose whether the rollup of tasks is done
Auto or Manual. When you
select "Manual," task dates are accepted as entered. Adjustments in children
tasks do not modify parent tasks or related dependent tasks. To roll up to
the related tasks in the schedule, a Project Leader clicks the Rollup icon
on the
project schedule toolbar.
Note the following behaviors for
"Manual" rollup:
- The rollup icon appears only when the project schedule mode is
“Manual."
- This capability is available only for projects and does not apply to
individual tasks, nor to related projects or subprojects that may have
dependencies to and from the project. Manual rollup is not available for
experiment or baseline projects. It is not available for projects in the
Gantt chart.
- Changes done in a predecessor task do not propagate to the successor
task.
- Constraint Type and Date are retained and these columns are read-only;
however, these values can get updated as a result of changes in the
Estimated Start/End Date. Constraint Type/Date values are not considered
while changing the estimated duration/start/finish dates of the
task.
- Manual rollup is available on cloud and mobile.
Percent complete based on. Choose whether project
completion percent is computed by task Duration or
Weightage. Only available in Planning View for a
project that is "In Work."
The project schedule and Gantt chart
reflect the same percent completed, based either on duration or weightage.
Because a subproject can be added under multiple projects, the percent
complete of a subproject is based on its own preference setting. However,
for a root project, a subproject contributes based on its weightage for the
root project.
The following behaviors apply for
"Weightage":
- You specify the task weight, in the Planning view of the Structured View
for a project. See Working the Structured View.
- When only a few tasks have 0 weightage, if all the tasks except 0
weightage tasks are completed, the percent complete of the project is
set to 99%.
- When all tasks have 0 weightage, the parent task/project percent
complete is set to 100% only when the last task is completed. Until
then, the percent complete of the parent task/project shows as 0%.
- A project that is created from a project template has project tasks with
the same weightage as the tasks in the project template.
- When a project baseline is created, "Project Baseline" tasks have the
same weightage as those of the "Project Space" tasks.
- Summary task completion based on weightage is calculated as
follows:
Table 1. Summary Task Example
|
|
Weightage |
% Complete |
Task-1 |
|
40 |
42 |
|
Task-11 |
40 |
30 |
|
Task-12 |
60 |
50 |
The % complete of summary task Task1 = Sum of the
multiplication of child tasks weightage and % Complete / Sum of
weightages of child tasks. In the above example, the calculation for
the completion of the summary task would be:
((40*30)+(60*50))/(40+60) = 42. Therefore, the % complete for Task-1
is 42.
Duration Unit. From the list, choose Days or
Hours as the project's default duration unit. The unit is pre-selected with
Days (but editable) when creating tasks. Does not show for a task.
Note:
If
you change the Duration Unit from Days to Hours, only the estimated days
are converted to hours and not the actual days. On the schedule page,
the hours are displayed for the estimated duration only for the project
row and summary tasks and not for all tasks.
Send Reminder.
From the list, choose the number of days before or after the
project due date that you want to send reminders. If you do not want to send
reminders, choose Do not send reminder.
Recurrence Interval. From the list, choose how often
you want to send reminders after the initial reminder. These intervals are
relative to the date chosen in the Send Reminder list. If you do not want to
send reminders, choose Do not send additional
reminders. Reminders are only sent if the project is not
completed.
Lag
Calendar. For projects in the "Preliminary" or "Ready"
state, you can select a lag calendar. The lag calendar is used to calculate
the delayed start and estimated end date of dependent tasks in a project.
The tasks of subproject use the lag calendar preference of the subproject
and not the root project.
- Predecessor Task Calendar. Calculates lag
based on the predecessor task. For example, for a lag of 2 days,
there is a delay of 2 days after the completion of the predecessor
task before the successor task can begin.
- Successor Task Calendar. Calculates lag based
on the successor task. For example, for a lag of 2 days, there is a
delay of 2 days after the completion of the successor task.
- Project Default Calendar. Calculates lag
based on the project default calendar.
Note:
When the Schedule is set to "Manual," a manual
refresh action is required after any preference or dependency changes. When
set to "Auto," the changes cause a rollup action.
Note:
If any change
occurs to the calendar of the task, you need to refresh manually or modify
the task date. This executes a rollup using the latest calendar
settings.
Resource Plan Mode. Sets the
default value for the page view to either Timeline or Phase. Once a resource
plan under a project has one or more resource requests defined, this setting
is no longer editable.
Effort Settings.
The following items control efforts on a project:
- Effort Notifications. Select TRUE to enable
email notification when efforts are submitted for approval.
- Effort Submission. Select whether efforts are
submitted at the Task level or
Phase level.
Assigned
Task Notification Setting. The following items control
notifications for assigned tasks:
- Send Reminder. From the list, choose the
number of days before or after the task due date that you want
reminders to be sent. If you do not want to send reminders, choose
Do not send reminder.
- Recurrence Interval. From the list, choose
how often you want to send reminders after the initial reminder.
These intervals are relative to the date chosen in the Send Reminder
list. If you do not want to send reminders, choose Do not
send additional reminders. You receive reminders
only if the task is not completed.
My Default Category and Tab. The
following items determine the default category and tab that you see after
you select a project:
- Default Category. If you select
Default, you see the project dashboard
highlighted in the navigation pane and the Schedule Status tab selected. If you
select Schedule, you see
Schedule selected in the navigation pane and you can select one of the schedule tabs in the Default
Tab field.
- Default Tab. If you selected
Schedule as the Default Category, select one
of these tabs to display: Structured View,
Flattened View, or Gantt
Chart.