Click
Enable Edit
.
You can click the risk name, risk factor name, or project name to see additional details.
-
For Risks, enter and change dates for risks as required. Click
to select a different date.
Estimated Start Date or
Estimated Finish Date. When creating a risk,
the originator enters these dates, but they may need to be changed as the risk
and assignee status changes.
Actual Start Date. Indicates when the risk
assignees began work on the risk. When an Actual Start Date is entered, the
system promotes the risk to Active. Alternatively, the risk owner/assignees can
promote the risk to Active and have the system automatically enter the current
date for the Actual Start Date.
Actual Finish Date.
Indicates when the risk assignees completed work on the
risk. When an Actual Finish Date is entered, the system promotes the risk to
Complete. Alternatively, the risk owner/assignees can promote the risk to
Complete and have the system automatically enter the current date for the
Actual Finish Date.
-
For risk factors, change one or more of the following values. Click
to
select a different date.
Impact. An estimate of the impact the risk has on the
project. The range is from 1 to 5, with 1 the lowest.
Probability. An estimate of how likely it is that the
risk will occur. The range is from 1 to 5, with 1 the lowest.
Effective Date. The date on which the risk factor
values take effect.
-
Click
Done.
|