				From the Authoring section of the
							action bar, click
					Process Gantt 
					 . .
- Select a system in the tree or System Editor.
			This can be the root system or a child system under the root system. Multi-Selection is not available. Only one system and its children are displayed in the
						Process Gantt. The image below shows an example of a Process Gantt chart:
  
 
 
 
- 
				Click Create Precedence Link
					 and select Loading Operation B then General Operation B in the Process Gantt
					chart. and select Loading Operation B then General Operation B in the Process Gantt
					chart.A  precedence constraint link appears in the Process
					Gantt chart between the two  operations.  Note:
			Another way of creating this
						type of constraint is by dragging and dropping one operation on the
						other. 
- 
				Select Create End-Start Link
					 and select
					Loading Operation C then General Operation C in the Process Gantt chart. In the
					pop-up that appears, specify a delay of 5 seconds between these two operations. and select
					Loading Operation C then General Operation C in the Process Gantt chart. In the
					pop-up that appears, specify a delay of 5 seconds between these two operations. A synchronization link appears in the Process Gantt chart between the two
						operations.   Note:
			Another way of creating this type of constraint is by dragging and
						dropping one operation on the other while pressing the
							Ctrl key. You then select Create
							End-Start Link
						 from the
							context toolbar that appears. from the
							context toolbar that appears.
 
- 
				Select General System C in the Process Gantt chart and
					click Unloading
					 . .In the Operation attributes dialog box that appears, enter an appropriate name
					and specify an estimated time of 2.5 seconds.  The new operation is created after the last operation in the selected system.
						  
- Create a precedence constraint link between General Operation C and the 
			Unloading Operation C that you just created.
			 The link appears in the Process Gantt chart between the two operations.   
 You can choose to display or hide precedence constraints and synchronization links in the
			Process Gantt chart. Right-click in the chart and select or clear the corresponding
			check box options in the context menu.