Creating a Simulation Activity from an Existing Activity
Instead of creating a new simulation activity, you will find it
easier in some cases to create an activity from an existing activity and change it
to suit your needs. When you create a simulation activity from an existing activity, all of the children
of the activity, such as its data categories, are also copied; however, referenced
documents continue to refer to their original documents.
Select the simulation process in which the activity will be created.
From the navigation pane, select Activities.
From the Activities table page that appears, toggle on the activity to copy.
From the table page toolbar, select Actions > Copy.
In the Copy page that appears, enter the following:
Title:Process Composer displays the title to indicate which activity you are working with.
You can change the title of the copied activity to help you distinguish between activities.
Revision: Enter the revision of the new activity. In most cases it will be the first revision in a new series.
Attribute Group: The attribute group from the original activity is inherited by the new activity.
Description: Enter a description that allows any user to determine the purpose of this activity.
Policy: Choose from the list of simulation activity policies. See About Policies for more information.
Click Done to create the simulation activity.
The new simulation activity appears in the Activities table page.
Note:
Any access rights that were granted to the original simulation activity are not copied over to the new activity.